Construction on the 19th Street and NW Cascade Ave project resumed on Monday, March 3, 2025. Contractors will work along the shoulders of 19th Street NW, which includes constructing retaining walls and relocating utilities. Impacts to traffic will include single-lane closure (with detour) and one-way traffic patterns through the project site, and will likely remain in place for the duration of the project, which is anticipated to continue until the end of June.
This road improvement project, led by the City of East Wenatchee, started last August and involves widening the roadways, installing bicycle lanes and sidewalks, and creating a new stormwater facility. To learn more about the project and to find recent updates, please visit City of East Wenatchee's project page.
Traffic impacts
Construction activities associated with the 19th Street and NW Cascade Ave project for the week of April 14th through April 18th are anticipated as follows:
Daytime impacts to traffic may include:
- Single-lane closure (with detour) and one-way traffic patterns through the project site on Monday (April 14th) through Friday (April 18th).
- Road closure (local access only) on 19th Street NE between Sunset Highway (SR28) and N Baker Ave tentatively Tuesday (April 15th) through Thursday (April 17th). Additional information regarding daytime road closure and detour route will be provided prior to implementation.
Nighttime work is anticipated to occur between 7-pm and 7-am on the evenings of Thursday April 17th through Friday April 18th. This work will include lane closures with detour. Detour route associated with nighttime work may vary depending on highway lane closures.
Construction activities associated with the 19th Street and NW Cascade Ave project for the week of April 14th through April 18th are anticipated as follows:
- Paving of Sunset Highway (SR28) at the 19th Street intersection (nighttime work).
- Utility work along 19th Street NW and Cascade Ave (daytime work).
- Watermain installation on 19th Street NW between NW Bates Avenue and Sunset Highway; and 19th Street NE between Sunset Highway and N Baker Avenue (daytime work).
Please note: Due to the nature of the utility installation work occurring next week, increased delays to traffic of up to 20-minutes may occur between NW Bates Ave and Sunset Highway (SR28) when work is occurring in that area.

Douglas County 19th Street Campus & Trailhead
The Douglas County Law & Justice Building, Public Services Building, and 19th Street NW Trailhead Access will remain open during road construction. Apple Capital Loop Trail users are encouraged to use the 27th Street NW Trailhead or 32nd Place Trailhead to avoid the construction area during this time.
Thank you for your patience!